FX-TDR-2611-001

Production Planning

Edit phases, crew and actual hours. Alerts compare against crew capacity and shop-wide load.

Planned hours
4,720
Actual to date
1,836
39% of plan
Duration
14 wks
Alerts
2

Timeline

W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
Material procurement
80% · 2 crew
Cutting & rolling
75% · 6 crew
Fit-up & welding
41% · 10 crew
NDT & PWHT
0% · 4 crew
Hydrotest & coating
0% · 6 crew
Shop load (all projects)

Phases & actuals

PhaseStart wkWeeksCrewPlanned hActual hVar.
-24
-180
-1,700
-380
-600

Capacity & bottleneck alerts

  • Shop week 6: load 1,918 h exceeds capacity 1,440 h (all projects)
  • Shop week 10: load 1,470 h exceeds capacity 1,440 h (all projects)

Shop capacity assumes 2 × default crew (12) × 6 shifts × 10 h — set in Settings.